WO-0008 Packaging Robot Cell
AST-0004
Robot cell E-stop fault, packaging halted. Integrator corrective urgent done
WO-0015 Air Compressor — Atlas 75kW
AST-0001
Compressor tripping on high temp mid-shift. K. Osei corrective high done
WO-0005 Conveyor Line 1
AST-0003
Conveyor drive motor overheating, line stopped. M. Reyes corrective high done
WO-0001 CNC Mill 3-Axis — Bay 2
AST-0002
Spindle vibration alarm at 8k RPM. M. Reyes corrective high done
WO-0014 Exhaust Fan EF-3
AST-0012
EF-3 squealing at startup. HVAC Crew corrective medium done
WO-0013 CNC Mill 3-Axis — Bay 2
AST-0002
PM: CNC way lube & coolant check. M. Reyes preventive medium done
WO-0010 Box Truck — Isuzu NPR
AST-0013
PM: Box truck DOT inspection prep. Fleet preventive medium done
WO-0009 Rooftop Unit RTU-2 (South)
AST-0010
RTU-2 short-cycling complaints, south offices hot. HVAC Crew corrective medium done
WO-0007 Dock Leveler #2
AST-0006
Dock leveler #2 drifting down under load. Dock Crew corrective medium done
WO-0006 Boiler — Weil 900 MBH
AST-0011
PM: Boiler blowdown & LWCO test. K. Osei preventive medium done
WO-0004 Forklift — Hyster H50
AST-0007
PM: Forklift 250h service. K. Osei preventive medium done
WO-0003 Rooftop Unit RTU-1 (North)
AST-0009
RTU-1 tripping on high pressure. HVAC Crew corrective medium done
WO-0002 Air Compressor — Atlas 75kW
AST-0001
PM: Compressor oil & separator change. K. Osei preventive medium done
WO-0012 Yard Sweeper
AST-0014
Yard sweeper brush motor intermittent. Fleet corrective low done
WO-0011 Dock Leveler #1
AST-0005
PM: Dock leveler lube & inspection. Dock Crew preventive low done
×